[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},984201,715,1,"单选题","项目生命周期中，计划阶段的主要工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","委托代理合同谈判与签订、招标前期准备",false,{"key":16,"text":17,"correct":18},"B","规划和设计招标活动、组建项目团队、制定定标策略",true,{"key":20,"text":21,"correct":14},"C","编制招标文件、发布招标公告、确定评标细则、抽取评标专家、组织开评标、撰写评标报告、推荐中标候选人、确定中标人、签订中标合同",{"key":23,"text":24,"correct":14},"D","检查、验收招标活动、合同执行和跟踪等","根据项目生命周期可以将招标过程质量控制分为启动、计划、实施和收尾四个阶段，每个阶段的质量控制目标和采取的措施有所不同。这四个阶段的主要工作分别是：①启动阶段，委托代理合同谈判与签订、招标前期准备；②计划阶段，规划和设计招标活动、组建项目团队、制定定标策略；③实施阶段，编制招标文件、发布招标公告、确定评标细则、抽取评标专家、组织开评标、撰写评标报告、推荐中标候选人、确定中标人、签订中标合同；④计划阶段，检查、验收招标活动、合同执行和跟踪等。",{"id":6,"name":27,"category":28,"favorite":7},"招标采购专业知识与法律法规","建筑工程"]