[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},984193,715,1,"单选题","影响工程采购策略制定的因素不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","履约能力",false,{"key":16,"text":17,"correct":14},"B","功能需求",{"key":19,"text":20,"correct":14},"C","履行期限",{"key":22,"text":23,"correct":24},"D","服务价格",true,"影响工程采购策略制定的因素一般包括：①施工价格；②功能需求；③履行期限；④履约能力。D项，服务价格属于影响服务采购策略制定的因素。",{"id":6,"name":27,"category":28,"favorite":7},"招标采购专业知识与法律法规","建筑工程"]