[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984186":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},984186,715,1,"单选题","工程项目招标的交易成本中，属于事中成本的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标直接成本",true,{"key":16,"text":17,"correct":18},"B","技术成本",false,{"key":20,"text":21,"correct":18},"C","价格成本",{"key":23,"text":24,"correct":18},"D","决策成本","根据交易过程的成本动因划分，工程项目招标过程中涉及招标人的交易成本主要包括：①事前成本；②事中成本；③事后成本。其中，事中成本包括：①招标直接成本；②评标成本；③政策成本。",{"id":6,"name":27,"category":28,"favorite":7},"招标采购专业知识与法律法规","建筑工程"]