[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-714-1":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":614},{"id":5,"name":6,"category":7,"favorite":8},714,"招标采购专业实务","建筑工程",0,1,50,865,[13,33,45,57,69,81,93,105,117,129,141,153,165,177,188,199,211,223,235,247,259,271,283,295,307,319,331,343,355,367,379,391,403,412,424,435,447,459,471,482,494,506,518,530,542,554,566,578,590,602],{"id":14,"libraryId":5,"type":9,"typeLabel":15,"stem":16,"options":17,"answer":26,"analysis":32},983243,"单选题","货物招标批次和招标时间顺序安排主要取决于货物的______，最终消费品的货物采购一般取决于______。()",[18,22,25,29],{"key":19,"text":20,"correct":21},"A","生产计划；货物的用途",false,{"key":23,"text":24,"correct":21},"B","进度要求；用户的实际需求时间",{"key":26,"text":27,"correct":28},"C","用途；用户的实际需求时间",true,{"key":30,"text":31,"correct":21},"D","市场需求量；进度要求","",{"id":34,"libraryId":5,"type":9,"typeLabel":15,"stem":35,"options":36,"answer":30,"analysis":32},983244,"关于招标人采购，下列叙述错误的是()。",[37,39,41,43],{"key":19,"text":38,"correct":21},"加大了招标人的采购控制权",{"key":23,"text":40,"correct":21},"加大了招标人的责任和风险",{"key":26,"text":42,"correct":21},"减轻了承包人相应的责任和风险",{"key":30,"text":44,"correct":28},"适用于工期比较短、规模较小或材料设备技术规格简单的工程建设项目",{"id":46,"libraryId":5,"type":9,"typeLabel":15,"stem":47,"options":48,"answer":19,"analysis":32},983245,"关于土地“招标、拍卖、挂牌”，下列说法错误的是()。",[49,51,53,55],{"key":19,"text":50,"correct":28},"招标的底价由委托人决定",{"key":23,"text":52,"correct":21},"招标的报价方式是填写投标书",{"key":26,"text":54,"correct":21},"挂牌不设立决策组织",{"key":30,"text":56,"correct":21},"拍卖的报价方式是现场举牌",{"id":58,"libraryId":5,"type":9,"typeLabel":15,"stem":59,"options":60,"answer":19,"analysis":32},983246,"一般标段较大的工程()。",[61,63,65,67],{"key":19,"text":62,"correct":28},"对投标人的资格条件要求较高",{"key":23,"text":64,"correct":21},"涉及的各种不确定因素较少",{"key":26,"text":66,"correct":21},"技术管理相对容易",{"key":30,"text":68,"correct":21},"招标文件的系统性、严密性相对较差",{"id":70,"libraryId":5,"type":9,"typeLabel":15,"stem":71,"options":72,"answer":19,"analysis":32},983247,"依据《岩土工程勘察规范》，下列不属于输气管道工程勘察阶段的是()。",[73,75,77,79],{"key":19,"text":74,"correct":28},"可行性研究勘察",{"key":23,"text":76,"correct":21},"选线勘察",{"key":26,"text":78,"correct":21},"初步勘察",{"key":30,"text":80,"correct":21},"详细勘察",{"id":82,"libraryId":5,"type":9,"typeLabel":15,"stem":83,"options":84,"answer":23,"analysis":32},983248,"从技术关联因素考虑标段划分的基本因素不包括()。",[85,87,89,91],{"key":19,"text":86,"correct":21},"工程技术关联性",{"key":23,"text":88,"correct":28},"工程设计关联性",{"key":26,"text":90,"correct":21},"工程计量的关联性",{"key":30,"text":92,"correct":21},"工作界面的合理性",{"id":94,"libraryId":5,"type":9,"typeLabel":15,"stem":95,"options":96,"answer":19,"analysis":32},983249,"()是科学、规范、有效地组织实施招标采购工作的必要基础和主要依据。",[97,99,101,103],{"key":19,"text":98,"correct":28},"招标方案",{"key":23,"text":100,"correct":21},"招标文件",{"key":26,"text":102,"correct":21},"招标方式",{"key":30,"text":104,"correct":21},"招标组织形式",{"id":106,"libraryId":5,"type":9,"typeLabel":15,"stem":107,"options":108,"answer":19,"analysis":32},983250,"某大型工程建设项目，已完成项目建议书。为了有效优化和控制项目投资，提高工程质量，缩短建设工期，下列招标方案中，最为理想的是()。",[109,111,113,115],{"key":19,"text":110,"correct":28},"组织工程设计施工一体化总承包招标",{"key":23,"text":112,"correct":21},"组织工程设计方案招标并论证确定后，再组织工程设计施工一体化总承包招标",{"key":26,"text":114,"correct":21},"按实施需求依次分别组织工程设计招标、工程施工招标",{"key":30,"text":116,"correct":21},"工程设计直接委托完成后，再组织工程施工和设备采购的招标",{"id":118,"libraryId":5,"type":9,"typeLabel":15,"stem":119,"options":120,"answer":23,"analysis":32},983251,"工程施工承包方式的典型模式为()。",[121,123,125,127],{"key":19,"text":122,"correct":21},"“设计+施工”",{"key":23,"text":124,"correct":28},"“设计一施工”",{"key":26,"text":126,"correct":21},"“设计采购建造”",{"key":30,"text":128,"correct":21},"“工厂设备与设计+施工”",{"id":130,"libraryId":5,"type":9,"typeLabel":15,"stem":131,"options":132,"answer":23,"analysis":32},983252,"在工程建设项目的主要外部因素中，工程设计和施工方案设计的主要技术依据是()。",[133,135,137,139],{"key":19,"text":134,"correct":21},"工程现场作业面条件",{"key":23,"text":136,"correct":28},"工程地形、地质和水文条件",{"key":26,"text":138,"correct":21},"工程施工进场道路和水电通信条件",{"key":30,"text":140,"correct":21},"工程周围原有建筑物",{"id":142,"libraryId":5,"type":9,"typeLabel":15,"stem":143,"options":144,"answer":26,"analysis":32},983253,"工程建设项目管理方式按组织管理方式可分为三类，其中不包括()。",[145,147,149,151],{"key":19,"text":146,"correct":21},"自主项目管理方式",{"key":23,"text":148,"correct":21},"委托专业项目管理方式",{"key":26,"text":150,"correct":28},"现代自主项目管理方式",{"key":30,"text":152,"correct":21},"特许经营和融资项目管理方式",{"id":154,"libraryId":5,"type":9,"typeLabel":15,"stem":155,"options":156,"answer":23,"analysis":32},983254,"房屋建筑和市政工程在施工图完成之后组织招标，其工程造价控制目标一般以()为限额。",[157,159,161,163],{"key":19,"text":158,"correct":21},"初步设计概算",{"key":23,"text":160,"correct":28},"施工图预算",{"key":26,"text":162,"correct":21},"投资估算",{"key":30,"text":164,"correct":21},"执行概算",{"id":166,"libraryId":5,"type":9,"typeLabel":15,"stem":167,"options":168,"answer":23,"analysis":32},983255,"下列各项不属于工程建设项目的是()。",[169,171,173,175],{"key":19,"text":170,"correct":21},"构筑物",{"key":23,"text":172,"correct":28},"勘察设计",{"key":26,"text":174,"correct":21},"建筑物",{"key":30,"text":176,"correct":21},"管道安装工程的改建",{"id":178,"libraryId":5,"type":9,"typeLabel":15,"stem":179,"options":180,"answer":30,"analysis":32},983256,"招标标段划分时，需考虑的主要因素不包括()。",[181,183,185,187],{"key":19,"text":182,"correct":21},"法律法规",{"key":23,"text":184,"correct":21},"工程承包管理模式",{"key":26,"text":186,"correct":21},"工程管理力量",{"key":30,"text":102,"correct":28},{"id":189,"libraryId":5,"type":9,"typeLabel":15,"stem":190,"options":191,"answer":19,"analysis":32},983257,"交通、铁道、石油化工、水利等工程建设项目在完成初步设计报告后组织招标，其工程造价控制目标一般以()为限额。",[192,194,196,197],{"key":19,"text":193,"correct":28},"工程初步设计概算",{"key":23,"text":195,"correct":21},"招标工程相应范围编制的执行概算",{"key":26,"text":160,"correct":21},{"key":30,"text":198,"correct":21},"工程设计概算",{"id":200,"libraryId":5,"type":9,"typeLabel":15,"stem":201,"options":202,"answer":26,"analysis":32},983258,"对于大型、复杂，并且安全系数及环保要求较高的工程建设项目，招标人需要编制()作为招标文件的附件。",[203,205,207,209],{"key":19,"text":204,"correct":21},"施工安全管理条例",{"key":23,"text":206,"correct":21},"施工安全规章制度",{"key":26,"text":208,"correct":28},"安全操作和环境管理规程",{"key":30,"text":210,"correct":21},"安全施工规范及要求",{"id":212,"libraryId":5,"type":9,"typeLabel":15,"stem":213,"options":214,"answer":19,"analysis":32},983259,"在开标程序中，无须由招标人或者其委托的招标代理机构的工作人员进行的是()。",[215,217,219,221],{"key":19,"text":216,"correct":28},"密封情况检查",{"key":23,"text":218,"correct":21},"拆封",{"key":26,"text":220,"correct":21},"唱标",{"key":30,"text":222,"correct":21},"记录并存档",{"id":224,"libraryId":5,"type":9,"typeLabel":15,"stem":225,"options":226,"answer":23,"analysis":32},983260,"关于招标组织形式，下列说法正确的是()。",[227,229,231,233],{"key":19,"text":228,"correct":21},"招标人不能自行招标",{"key":23,"text":230,"correct":28},"优先考虑委托代理招标",{"key":26,"text":232,"correct":21},"即使没有专职招标人员，招标人也可以自行招标",{"key":30,"text":234,"correct":21},"自行招标便于协调管理",{"id":236,"libraryId":5,"type":9,"typeLabel":15,"stem":237,"options":238,"answer":26,"analysis":32},983261,"某商场工程建设项目招标，比较合理的招标顺序是()。",[239,241,243,245],{"key":19,"text":240,"correct":21},"①扶梯及电梯采购、②工程施工、③工程设计、④灯具采购",{"key":23,"text":242,"correct":21},"①工程施工、②工程设计、③扶梯及电梯采购、④灯具采购",{"key":26,"text":244,"correct":28},"①工程设计、②扶梯及电梯采购、③工程施工、④灯具采购",{"key":30,"text":246,"correct":21},"①工程设计、②灯具采购、③工程施工、④扶梯及电梯采购",{"id":248,"libraryId":5,"type":9,"typeLabel":15,"stem":249,"options":250,"answer":26,"analysis":32},983262,"按照工程项目建设程序，下列投资控制目标排列顺序正确的是()。",[251,253,255,257],{"key":19,"text":252,"correct":21},"投资估算、设计概算、施工图预算、竣工决算、合同价格",{"key":23,"text":254,"correct":21},"设计概算、投资估算、施工图预算、竣工决算、中标价格",{"key":26,"text":256,"correct":28},"投资估算、设计概算、施工图预算、合同价格、竣工决算",{"key":30,"text":258,"correct":21},"设计概算、投资估算、施工图预算、合同价格、竣工决算",{"id":260,"libraryId":5,"type":9,"typeLabel":15,"stem":261,"options":262,"answer":26,"analysis":32},983263,"工程建设项目中某些大宗的、重要的、新型特殊设备材料适用()方式。",[263,265,267,269],{"key":19,"text":264,"correct":21},"承包人采购",{"key":23,"text":266,"correct":21},"招标人与承包人联合采购",{"key":26,"text":268,"correct":28},"招标人采购",{"key":30,"text":270,"correct":21},"招标人自行制造",{"id":272,"libraryId":5,"type":9,"typeLabel":15,"stem":273,"options":274,"answer":19,"analysis":32},983264,"与发包人采购相比，由承包人采购工程材料设备具有()的特点。",[275,277,279,281],{"key":19,"text":276,"correct":28},"便于实现采购和工程的系统化管理",{"key":23,"text":278,"correct":21},"采购和结算操作管理相对复杂",{"key":26,"text":280,"correct":21},"仅适合简单的工程",{"key":30,"text":282,"correct":21},"适合于材料设备技术相对复杂的工程",{"id":284,"libraryId":5,"type":9,"typeLabel":15,"stem":285,"options":286,"answer":26,"analysis":32},983265,"根据《工程建设项目货物招标投标办法》的规定，对无法精确拟定其技术规格的货物，招标人可以()。",[287,289,291,293],{"key":19,"text":288,"correct":21},"不招标",{"key":23,"text":290,"correct":21},"直接采购",{"key":26,"text":292,"correct":28},"采用两阶段招标程序",{"key":30,"text":294,"correct":21},"邀请招标",{"id":296,"libraryId":5,"type":9,"typeLabel":15,"stem":297,"options":298,"answer":26,"analysis":32},983266,"货物的()能体现货物的通用性、可替换性，备品备件的易得性。",[299,301,303,305],{"key":19,"text":300,"correct":21},"技术特征",{"key":23,"text":302,"correct":21},"质量",{"key":26,"text":304,"correct":28},"产品标准化水平",{"key":30,"text":306,"correct":21},"功能",{"id":308,"libraryId":5,"type":9,"typeLabel":15,"stem":309,"options":310,"answer":26,"analysis":32},983267,"确定工程货物招标顺序的主要因素不包括()。",[311,313,315,317],{"key":19,"text":312,"correct":21},"工程建设项目进度要求或项目业主对货物的实际需求时间",{"key":23,"text":314,"correct":21},"货物的生产和供应周期",{"key":26,"text":316,"correct":28},"货物的数量需求",{"key":30,"text":318,"correct":21},"完成招标程序所需要的时间",{"id":320,"libraryId":5,"type":9,"typeLabel":15,"stem":321,"options":322,"answer":19,"analysis":32},983268,"某铁路工程建设项目，由于前期拆迁拖延，延误了建设工期。在满足其他条件的情况下，为缩短工期，招标人可以采取的措施是()。",[323,325,327,329],{"key":19,"text":324,"correct":28},"适当增加工程施工招标标段的数量",{"key":23,"text":326,"correct":21},"同时组织初步设计招标和施工招标",{"key":26,"text":328,"correct":21},"安排具备资质的承包人进场施工，同时办理招标手续",{"key":30,"text":330,"correct":21},"先发出招标文件，在开标前一周内补充设计技术参数",{"id":332,"libraryId":5,"type":9,"typeLabel":15,"stem":333,"options":334,"answer":23,"analysis":32},983269,"下列各项不属于货物需求目标的是()。",[335,337,339,341],{"key":19,"text":336,"correct":21},"货物的服务需求",{"key":23,"text":338,"correct":28},"货物的耐用性需求",{"key":26,"text":340,"correct":21},"货物的价格需求",{"key":30,"text":342,"correct":21},"货物的供应进度需求",{"id":344,"libraryId":5,"type":9,"typeLabel":15,"stem":345,"options":346,"answer":23,"analysis":32},983270,"()是社会资本方负责项目融资、建设、运营，运营期满后，社会资本方将该项目移交给政府部门的招标方式。",[347,349,351,353],{"key":19,"text":348,"correct":21},"PPP",{"key":23,"text":350,"correct":28},"BOT",{"key":26,"text":352,"correct":21},"TOT",{"key":30,"text":354,"correct":21},"BT",{"id":356,"libraryId":5,"type":9,"typeLabel":15,"stem":357,"options":358,"answer":26,"analysis":32},983271,"招标人按照招标采购方式选择的中标货物价格以及据此签订的采购合同价格是()。",[359,361,363,365],{"key":19,"text":360,"correct":21},"货物预算价格",{"key":23,"text":362,"correct":21},"货物概算金额",{"key":26,"text":364,"correct":28},"货物采购价格",{"key":30,"text":366,"correct":21},"货物决算价格",{"id":368,"libraryId":5,"type":9,"typeLabel":15,"stem":369,"options":370,"answer":30,"analysis":32},983272,"关于招标方案与项目管理及合同规划的关系，下列说法不正确的是()。",[371,373,375,377],{"key":19,"text":372,"correct":21},"招标方案与招标项目管理方案的工作对象不同",{"key":23,"text":374,"correct":21},"招标方案是招标项目管理方案的重要组成内容",{"key":26,"text":376,"correct":21},"招标方案是一个招标项目一次招标组织实施工作的总体策划",{"key":30,"text":378,"correct":28},"招标人应当依据整个项目最终的招标方案，调整、补充和细化形成该招标方案中的招标采购合同规划",{"id":380,"libraryId":5,"type":9,"typeLabel":15,"stem":381,"options":382,"answer":19,"analysis":32},983273,"工程建设项目招标人自行办理招标事宜，须具备()和组织评标的能力。",[383,385,387,389],{"key":19,"text":384,"correct":28},"编制招标文件",{"key":23,"text":386,"correct":21},"委托招标代理机构",{"key":26,"text":388,"correct":21},"编制招标标底",{"key":30,"text":390,"correct":21},"编制招标公告",{"id":392,"libraryId":5,"type":9,"typeLabel":15,"stem":393,"options":394,"answer":19,"analysis":32},983274,"反映工程构造的直接依据是()。",[395,397,399,401],{"key":19,"text":396,"correct":28},"设计图纸",{"key":23,"text":398,"correct":21},"施工方案",{"key":26,"text":400,"correct":21},"设计方案",{"key":30,"text":402,"correct":21},"技术规范",{"id":404,"libraryId":5,"type":9,"typeLabel":15,"stem":405,"options":406,"answer":30,"analysis":32},983275,"下列各项不属于材料设备的采购供应方式的是()。",[407,408,409,410],{"key":19,"text":268,"correct":21},{"key":23,"text":264,"correct":21},{"key":26,"text":266,"correct":21},{"key":30,"text":411,"correct":28},"第三方采购供货",{"id":413,"libraryId":5,"type":9,"typeLabel":15,"stem":414,"options":415,"answer":19,"analysis":32},983276,"招标人的工程管理力量比较薄弱，协调管理能力也不强，则划分标段时招标人()。",[416,418,420,422],{"key":19,"text":417,"correct":28},"不宜划分过多的标段",{"key":23,"text":419,"correct":21},"不宜划分过少的标段",{"key":26,"text":421,"correct":21},"不应划分为不同的标段",{"key":30,"text":423,"correct":21},"可不考虑自身工程管理力量、协调管理能力的因素",{"id":425,"libraryId":5,"type":9,"typeLabel":15,"stem":426,"options":427,"answer":30,"analysis":32},983277,"工程建设项目设计招标文件中通常给出项目可行性研究报告中的()，作为投资人实施工程设计控制和优化的目标依据。",[428,430,431,433],{"key":19,"text":429,"correct":21},"技术设计概算",{"key":23,"text":158,"correct":21},{"key":26,"text":432,"correct":21},"工程投资概算",{"key":30,"text":434,"correct":28},"工程投资限额",{"id":436,"libraryId":5,"type":9,"typeLabel":15,"stem":437,"options":438,"answer":23,"analysis":32},983278,"工程建设项目管理和承包方式中，适用于招标人愿意较深入地介入设计控制及对设计和施工进行相互协调管理，并希望分散承担风险的情况的是()。",[439,441,443,445],{"key":19,"text":440,"correct":21},"“设计+施工”模式",{"key":23,"text":442,"correct":28},"“设计一施工”模式",{"key":26,"text":444,"correct":21},"“设计采购建造”模式",{"key":30,"text":446,"correct":21},"“工厂设备与设计+施工”模式",{"id":448,"libraryId":5,"type":9,"typeLabel":15,"stem":449,"options":450,"answer":23,"analysis":32},983279,"对投标人的资格条件没有特别的规定，一般要求具有较强的融资实力、比较丰富的管理经验和较强的专业能力的招标方式是()。",[451,453,455,457],{"key":19,"text":452,"correct":21},"PPP项目招标",{"key":23,"text":454,"correct":28},"BOT项目招标",{"key":26,"text":456,"correct":21},"TOT项目招标",{"key":30,"text":458,"correct":21},"股权融资招标",{"id":460,"libraryId":5,"type":9,"typeLabel":15,"stem":461,"options":462,"answer":19,"analysis":32},983280,"下列对设计施工一体化承包方式的描述，错误的是()。",[463,465,467,469],{"key":19,"text":464,"correct":28},"承包人和分包人不对分包工程承担连带责任",{"key":23,"text":466,"correct":21},"典型模式有“工厂设备与设计+施工”",{"key":26,"text":468,"correct":21},"适用于规模大、专业技术性强的工程建设项目",{"key":30,"text":470,"correct":21},"可以合理组织分段设计与施工，缩短建设工期",{"id":472,"libraryId":5,"type":9,"typeLabel":15,"stem":473,"options":474,"answer":19,"analysis":32},983281,"工程建设项目造价控制的第一个关键阶段是()。",[475,477,479,480],{"key":19,"text":476,"correct":28},"设计概算",{"key":23,"text":478,"correct":21},"工程施工招标形成工程中标合同价格",{"key":26,"text":193,"correct":21},{"key":30,"text":481,"correct":21},"工程建设项目可行性研究投资估算",{"id":483,"libraryId":5,"type":9,"typeLabel":15,"stem":484,"options":485,"answer":19,"analysis":32},983282,"招标是否编制标底由()自主决定。",[486,488,490,492],{"key":19,"text":487,"correct":28},"招标人",{"key":23,"text":489,"correct":21},"招标代理机构",{"key":26,"text":491,"correct":21},"承包商",{"key":30,"text":493,"correct":21},"政府有关行政部门",{"id":495,"libraryId":5,"type":9,"typeLabel":15,"stem":496,"options":497,"answer":30,"analysis":32},983283,"工程承包方式主要有()方式。",[498,500,502,504],{"key":19,"text":499,"correct":21},"分包与总包",{"key":23,"text":501,"correct":21},"专业分包与劳务分包",{"key":26,"text":503,"correct":21},"施工承包与设计承包",{"key":30,"text":505,"correct":28},"施工承包和设计一施工一体化承包",{"id":507,"libraryId":5,"type":9,"typeLabel":15,"stem":508,"options":509,"answer":30,"analysis":32},983284,"货物与工程的最显著区别在于货物具有()。",[510,512,514,516],{"key":19,"text":511,"correct":21},"产品的多样性",{"key":23,"text":513,"correct":21},"技术性",{"key":26,"text":515,"correct":21},"来源的广泛性",{"key":30,"text":517,"correct":28},"可移动性",{"id":519,"libraryId":5,"type":9,"typeLabel":15,"stem":520,"options":521,"answer":23,"analysis":32},983285,"具有特殊的配建项目或特殊需求的国有建设用地，比较合适的土地出让方式是()。",[522,524,526,528],{"key":19,"text":523,"correct":21},"划拨",{"key":23,"text":525,"correct":28},"招标",{"key":26,"text":527,"correct":21},"拍卖",{"key":30,"text":529,"correct":21},"挂牌",{"id":531,"libraryId":5,"type":9,"typeLabel":15,"stem":532,"options":533,"answer":19,"analysis":32},983286,"工程建设项目管理的四大控制目标中，()是反映工程产品满足使用需求功能特性的总和。",[534,536,538,540],{"key":19,"text":535,"correct":28},"工程质量",{"key":23,"text":537,"correct":21},"工程进度",{"key":26,"text":539,"correct":21},"工程造价",{"key":30,"text":541,"correct":21},"工程安全",{"id":543,"libraryId":5,"type":9,"typeLabel":15,"stem":544,"options":545,"answer":19,"analysis":32},983287,"建设工程勘察费用应()。",[546,548,550,552],{"key":19,"text":547,"correct":28},"依据监理范围内的投资额",{"key":23,"text":549,"correct":21},"遵循国家相关收费规定",{"key":26,"text":551,"correct":21},"由业主方确定",{"key":30,"text":553,"correct":21},"由监理单位确定",{"id":555,"libraryId":5,"type":9,"typeLabel":15,"stem":556,"options":557,"answer":23,"analysis":32},983288,"工程承包方式中，一般适用于工程建设项目规模大、专业技术性强、管理协调工作复杂、招标人对设计施工的管理力量薄弱的工程的是()。",[558,560,562,564],{"key":19,"text":559,"correct":21},"施工承包方式",{"key":23,"text":561,"correct":28},"设计施工一体化承包方式",{"key":26,"text":563,"correct":21},"特许经营和融资项目管理与承包方式",{"key":30,"text":565,"correct":21},"“建造一经营一转让”承包方式",{"id":567,"libraryId":5,"type":9,"typeLabel":15,"stem":568,"options":569,"answer":23,"analysis":32},983289,"采用资格预审方法招标的主要缺点是()。",[570,572,574,576],{"key":19,"text":571,"correct":21},"增加了评标费用",{"key":23,"text":573,"correct":28},"增加了招标投标流程",{"key":26,"text":575,"correct":21},"延长了评标时间",{"key":30,"text":577,"correct":21},"不适合技术复杂的招标项目",{"id":579,"libraryId":5,"type":9,"typeLabel":15,"stem":580,"options":581,"answer":23,"analysis":32},983290,"资格预审的合格制是指()。",[582,584,586,588],{"key":19,"text":583,"correct":21},"一定数量的预审通过者获得投标资格",{"key":23,"text":585,"correct":28},"满足资格预审文件规定资格审查标准的申请人均获得投标资格",{"key":26,"text":587,"correct":21},"通过初审的申请人均可进入详细评审阶段",{"key":30,"text":589,"correct":21},"一定数量的初步评审通过者可进入详细评审阶段",{"id":591,"libraryId":5,"type":9,"typeLabel":15,"stem":592,"options":593,"answer":19,"analysis":32},983291,"在工程建设项目货物招标项目中，一个制造商对同一品牌同一型号的货物，可以委托()代理商参加投标。",[594,596,598,600],{"key":19,"text":595,"correct":28},"一个",{"key":23,"text":597,"correct":21},"二个",{"key":26,"text":599,"correct":21},"两个以上",{"key":30,"text":601,"correct":21},"任意",{"id":603,"libraryId":5,"type":9,"typeLabel":15,"stem":604,"options":605,"answer":30,"analysis":32},983292,"工程施工招标项目资格预审文件的内容不包括()。",[606,608,610,612],{"key":19,"text":607,"correct":21},"资格预审公告",{"key":23,"text":609,"correct":21},"申请人须知",{"key":26,"text":611,"correct":21},"资格预审申请文件格式",{"key":30,"text":613,"correct":28},"主要技术人员简历",[615,618,621,624,627,630],{"id":9,"name":616,"category":7,"favorite":617},"领导干部任职前廉政法规知识测试题",92,{"id":619,"name":620,"category":7,"favorite":9},595,"建筑结构与设备",{"id":622,"name":623,"category":7,"favorite":9},715,"招标采购专业知识与法律法规",{"id":625,"name":626,"category":7,"favorite":9},848,"市政方向-通用基础",{"id":628,"name":629,"category":7,"favorite":8},534,"BIM工程师",{"id":631,"name":629,"category":7,"favorite":8},535]