[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983992":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983992,714,2,"多选题","国际竞争性招标采购，下列情形中，需要得到世界银行批准的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","重新招标",true,{"key":16,"text":17,"correct":14},"B","拒绝所有投标",{"key":19,"text":20,"correct":21},"C","与低于成本价投标人签订合同",false,{"key":23,"text":24,"correct":21},"D","投标截止时投标人少于3家开标",{"key":26,"text":27,"correct":14},"E","与超过采购预算的最低评标价的投标人进行价格谈判","ABE","世行、亚行不允许单纯为了获得更低的价格而拒绝所有投标，而重新招标却又使用相同的招标文件和合同文件。如果最低评标价大大超过招标人更新后的费用估算，招标人应调查费用过高的原因，并考虑重新招标。招标人也可与最低评标价的投标人进行谈判，以尝试通过缩小合同范围或重新分配风险和责任来获取满意的合同，而这些缩小和重新分配应能够降低合同价。但是，对合同范围的实质性缩小或对合同文件的实质性修改可能需要重新招标。在拒绝所有投标、重新招标或与最低评标价的投标人进行谈判之前，应征得世行、亚行的不反对意见。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]