[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983986":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983986,714,2,"多选题","在利用外国政府贷款的项目中，下列关于选择采购代理公司的说法正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","省级发展改革委部门组织或指导、监督采购人进行采购代理公司招标工作",false,{"key":16,"text":17,"correct":14},"B","采购人应向3家以上（不含3家）采购代理公司同时发出投标邀请书",{"key":19,"text":20,"correct":21},"C","采购代理公司提交代理申请书的截止时间为自投标邀请书发出之日起至代理申请书送达借款人之日止不少于10个工作日",true,{"key":23,"text":24,"correct":21},"D","如第二次招标后收到代理申请书的采购代理公司累计仍少于3家，则不必重新发出邀请，可在已收到代理申请书的采购代理公司范围内进行评标",{"key":26,"text":27,"correct":21},"E","采购代理公司可按自愿协商的原则联合投标","CDE","A项，地方财政部门收到财政部通知后，组织或指导、监督采购人进行采购代理公司招标工作，所有贷款项目的采购代理公司招标工作须在财政部发出通知之日起40个工作日内完成。B项，采购人应向3家以上（含3家）采购代理公司同时发出投标邀请书。涉及2个以上子项目的打捆项目应作为一个项目发出投标邀请书。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]