[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983964":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983964,714,2,"多选题","下列关于评标委员会的各种评标办法顺序的说法中，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用最低评标价法的，按投标报价由高到低顺序排列",false,{"key":16,"text":17,"correct":18},"B","采用综合评分法的，按评审后得分由高到低顺序排列；得分相同时，按投标报价由低到高顺序排列；得分且投标报价相同时，按技术指标优劣顺序排列",true,{"key":20,"text":21,"correct":18},"C","采用最低评标价法的，投标报价相同的，按技术指标优劣顺序排列",{"key":23,"text":24,"correct":18},"D","采用性价比法的，投标得分相同的，按投标报价由低到高顺序排列；投标得分且投标报价相同的，按技术指标优劣顺序排列",{"key":26,"text":27,"correct":14},"E","采用综合评分法的，按评审后得分由低到高顺序排列；得分相同的，按投标报价由低到高顺序排列；得分且投标报价相同的，按技术指标优劣顺序排列","BCD","A项，采用最低评标价法的，按投标报价由低到高顺序排列；投标报价相同的，按技术指标优劣顺序排列。E项，采用综合评分法的，按评分从高到低排序，评审得分相同时，按投标报价由低到高顺序排列；得分且投标报价相同时，按技术指标优劣顺序排列。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]