[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983949":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983949,714,2,"多选题","某国有企业利用自有资金采用国际招标采购机床设备，投标截止时投标人只有2家。对此，招标代理机构的下列做法中正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","重新招标",true,{"key":16,"text":17,"correct":14},"B","顺延投标截止时间，并在指定的媒体上发布变更公告",{"key":19,"text":20,"correct":21},"C","顺延投标截止时间，应当在投标截止时间前，将变更时间书面通知所有潜在投标人",false,{"key":23,"text":24,"correct":14},"D","重新招标后投标人仍不足3个的，可以进行两家或一家开标评标",{"key":26,"text":27,"correct":21},"E","无需审批、核准，可以不再进行招标","ABD","机电产品国际招标项目因投标人少于3个不予开标或开标后由评标委员会认定投标人少于3个而终止评标的，应当重新招标。重新招标后投标人仍不足3个的，可以进行两家或一家开标评标；按国家有关规定需要履行审批、核准手续的依法必须进行招标的项目，报项目审批、核准部门审批、核准后可以不再进行招标。机电产品国际招标项目、政府采购货物和服务招标项目，招标人如果顺延投标截止时间，应当在招标文件规定的提交投标文件截止时间3日前，将变更时间书面通知所有获取招标文件的潜在投标人，并在指定的媒体上发布变更公告。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]