[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983923":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983923,714,2,"多选题","投标人在决定参与投标之前，应当对可能影响投标的内在因素和外在因素进行分析，作出投标决策。其中，外在因素包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","投标人资格",false,{"key":16,"text":17,"correct":14},"B","投标人业绩",{"key":19,"text":20,"correct":21},"C","市场竞争格局",true,{"key":23,"text":24,"correct":14},"D","设备",{"key":26,"text":27,"correct":21},"E","项目需求特征","CE","投标人在决定参与投标之前，应当对可能影响投标的内在因素和外在因素进行分析，作出投标决策。其中，内在因素包括投标人资格、业绩、人员、设备等，外在因素包括项目需求特征和市场竞争格局等。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]