[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983910":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983910,714,2,"多选题","施工组织设计除采用文字表述外，还应按照招标文件规定的格式编写()等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投入本标段的主要施工设备表",true,{"key":16,"text":17,"correct":18},"B","施工图纸",false,{"key":20,"text":21,"correct":14},"C","劳动计划表",{"key":23,"text":24,"correct":14},"D","计划开工竣工日期",{"key":26,"text":27,"correct":14},"E","施工进度网络图","ACDE","施工组织设计除采用文字表述外，还应按照招标文件规定的格式编写：①拟投入本标段的主要施工设备表；②拟配备本标段的试验和检测仪器设备表；③劳动计划表；④计划开工竣工日期；⑤施工进度网络图；⑥施工总平面图；⑦临时用地表等。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]