[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983907":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983907,714,2,"多选题","采用工程量清单报价时，投标人应考虑的因素有()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","招标文件中的计价要求",true,{"key":16,"text":17,"correct":14},"B","施工现场实际情况",{"key":19,"text":20,"correct":14},"C","施工组织设计",{"key":22,"text":23,"correct":14},"D","要素价格信息",{"key":25,"text":26,"correct":27},"E","竞争对手的情况",false,"ABCD","工程量清单报价是投标人根据招标文件提供的招标工程量清单内容格式以及计价要求，结合施工现场实际情况及其为招标项目编制的施工组织设计，按照企业定额或参照政府主管部门颁布的计价定额，结合市场人工、材料、机械等要素价格以及自身竞争能力进行投标报价。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]