[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983888":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983888,714,2,"多选题","某施工总承包合同为固定总价合同，一般可以调整价格的情况有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","主材价格发生变化",false,{"key":16,"text":17,"correct":18},"B","工程设计变更",true,{"key":20,"text":21,"correct":18},"C","范围调整",{"key":23,"text":24,"correct":14},"D","人工费上涨",{"key":26,"text":27,"correct":14},"E","中标工程量与设计图纸不一致的调整","BC","总价合同是指在合同中确定完成一个项目的总价，承包人据此完成项目全部内容的合同。总价合同情况下，招标人提供的工程量清单仅供投标人参考，投标人自行计算核定工程量。总价合同的工程数量、单价及总价一般不变，除约定的合同范围调整或者设计变更可以调整总价之外，也可约定人工、材料和设备等部分要素价格波动依据约定的指数调整总价，除此之外的其他风险则由承包人承担。总价合同一般适用于工程规模较小、技术比较简单、工期较短（一般不超过一年）、具备完整详细设计文件的工程建设项目。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]