[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983885":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983885,714,2,"多选题","经评审的最低投标价法和综合评估法都需要计算评标价格，计算评标价格时需要考虑()因素的一致性。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","报价范围",true,{"key":16,"text":17,"correct":18},"B","报价准确性",false,{"key":20,"text":21,"correct":14},"C","包含费用",{"key":23,"text":24,"correct":14},"D","付款进度",{"key":26,"text":27,"correct":18},"E","付款数量","ACD","评标价格是指经过对投标报价的报价范围、包含费用和付款进度的调整，得出评审后的投标价格。计算评标价格需要考虑报价范围、包含费用和付款进度等因素的一致性。其中，报价范围的一致性主要考量报价是否包含了招标文件要求的各项内容；包含费用的一致性主要是考量、调整，使价格术语不同、交货地点不同、包含费用不同的报价所包含的费用一致；付款进度的一致性主要考量资金的时间价值。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]