[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983868":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983868,714,2,"多选题","世界银行、亚洲开发银行贷款项目采用最低评标价法进行价格和非价格要素折算时，与价格不直接相关的商务要素包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资信",true,{"key":16,"text":17,"correct":18},"B","施工方案",false,{"key":20,"text":21,"correct":14},"C","企业实力",{"key":23,"text":24,"correct":18},"D","服务承诺",{"key":26,"text":27,"correct":14},"E","人员经验","ACE","世界银行、亚洲开发银行贷款项目、机电产品国际招标项目采用的最低评标价法，是将投标报价、商务和技术因素全部折算为价格，把折算后的累计价格（即评审后价格）进行比较，评审后价格最低的为最优投标。这种评标方法除了对投标的价格要素进行折算外，还把与价格不直接相关的商务要素（包括资信、资质、业绩、企业实力、人员经验等）和技术要素（包括施工方案、施工组织设计、技术指标、服务承诺等）等非价格要素按照招标文件规定的办法进行价格折算。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]