[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983861":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983861,714,2,"多选题","工程施工合同按照合同计价方式和风险分担情况可分为()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总价合同",true,{"key":16,"text":17,"correct":18},"B","固定收益合同",false,{"key":20,"text":21,"correct":14},"C","单价合同",{"key":23,"text":24,"correct":14},"D","成本加酬金合同",{"key":26,"text":27,"correct":18},"E","分包合同","ACD","工程施工合同按照合同计价方式和风险分担情况划分为：①总价合同，指在合同中确定完成一个项目的总价，承包人据此完成项目全部内容的合同。②单价合同，是由发包人提供工程量清单，承包人据此填报单价所形成的合同，其特点为工程量的变化风险由发包人承担，单价风险由承包人承担。单价合同也可约定部分要素价格依据相应指数波动调整单价。③成本加酬金合同，指合同价格中工程成本按照实际发生额计算确定和支付，承包人的酬金可以按照合同双方约定额度或者比例的工程管理服务费和利润额计算确定，或按照工程成本、质量、进度的控制结果挂钩奖惩的浮动比例计算核定。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]