[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983820":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983820,714,2,"多选题","工程建设项目概况中，项目说明应首先概要介绍工程建设项目的()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目业主",false,{"key":16,"text":17,"correct":18},"B","预期效益",true,{"key":20,"text":21,"correct":18},"C","建设任务",{"key":23,"text":24,"correct":14},"D","资金来源",{"key":26,"text":27,"correct":18},"E","工程规模标准","BCE","工程建设项目概况的内容应包括项目说明、建设条件、建设要求和其他需要说明的情况。其中，项目说明首先应概要介绍工程建设项目的建设任务、工程规模标准和预期效益；其次说明项目的批准或核准情况；再次介绍该工程的项目业主，项目投资人出资比例，以及资金来源；最后概要介绍项目的建设地点、计划工期、招标范围和标段划分情况。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]