[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983814":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983814,714,2,"多选题","当其他条件相同时，缩小工程施工招标的标段划分规模，可能会()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","减少大型企业投标的数量",true,{"key":16,"text":17,"correct":14},"B","增加工程承包人的固定成本比例",{"key":19,"text":20,"correct":21},"C","减少招标的工程管理工作量",false,{"key":23,"text":24,"correct":21},"D","减少标段工程造价竞争的空间",{"key":26,"text":27,"correct":14},"E","延长标段工程施工工期","ABE","标段规模小，标段数量多，进场施工的承包人多，容易集中各承包人加快投入更多的资源力量，在多个工点齐头并进赶工期，但需要项目发包人具有相应的管理力量配合以及充足、及时的资金保障。标段数量增加虽然能引进更多承包人进场施工，但也可能因标段规模偏小，发挥不了规模效益，不利于吸引大型施工企业参与投标，也不利于发挥大型施工机械的使用效率，从而提高工程造价，并容易导致产生转包、分包现象。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]