[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983804":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983804,714,2,"多选题","工程建设项目进度控制包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","编制工程建设进度计划",true,{"key":16,"text":17,"correct":14},"B","确定各阶段的建设工作内容、工作程序、工作时间和衔接关系",{"key":19,"text":20,"correct":14},"C","制定相应控制、预防或补救措施",{"key":22,"text":23,"correct":24},"D","制定科学、合理的招标工程建设项目进度目标和计划要求",false,{"key":26,"text":27,"correct":24},"E","适时调整和修改进度计划","ABC","工程进度控制，是指工程建设的进度目标以及为实现这一目标所采取的一系列控制方法和措施，包括：①编制工程建设进度计划；②确定各阶段的建设工作内容、工作程序、工作时间和衔接关系；③制定相应控制、预防或补救措施。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]