[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983800":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983800,714,2,"多选题","水电工程建设项目设计一般分为()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","预可行性研究",true,{"key":16,"text":17,"correct":14},"B","可行性研究",{"key":19,"text":20,"correct":14},"C","招标设计",{"key":22,"text":23,"correct":24},"D","初步设计",false,{"key":26,"text":27,"correct":14},"E","施工图设计","ABCE","水电工程建设项目设计一般划分为预可行性研究、可行性研究、招标设计和施工图设计三个阶段，其招标设计阶段相当于建筑行业的初步设计阶段。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]