[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983798":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983798,714,2,"多选题","下列关于材料设备由承包人采购的方式，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","加大了招标人的责任和风险",false,{"key":16,"text":17,"correct":18},"B","采购和结算操作管理简单",true,{"key":20,"text":21,"correct":18},"C","较适用于工期较短、规模较小的工程建设项目",{"key":23,"text":24,"correct":14},"D","加大了招标人的采购控制权",{"key":26,"text":27,"correct":18},"E","适用于材料设备技术规格简单的工程建设项目","BCE","承包人采购的方式与招标人采购供货方式的利弊关系正好相反，责任风险均由承包人承担，采购和结算操作管理简单。这种方式比较适用于工期比较短、规模较小或材料设备技术规格简单的工程。工期较长的大型工程，如由承包人采购材料设备，宜在合同条款中设置相应材料设备的价格调整条款，以减少价格波动给承包人带来的过多风险。AD两项属于招标人自行采购供货的特点。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]