[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983787":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983787,714,2,"多选题","工程建设项目造价控制，一般按建设程序划分为()目标形式。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程可行性研究投资估算",true,{"key":16,"text":17,"correct":14},"B","工程初步设计概算",{"key":19,"text":20,"correct":21},"C","工程技术概算造价",false,{"key":23,"text":24,"correct":14},"D","工程施工图预算造价",{"key":26,"text":27,"correct":14},"E","工程结算造价与竣工决算投资","ABDE","工程建设项目造价控制目标和形式与工程建设程序密切相关。工程建设的不同阶段具有各自的造价控制目标和形式。一般按建设程序划分为四种目标形式：①工程可行性研究阶段的投资估算；②初步设计阶段的设计概算；③施工图设计阶段的施工图预算；④竣工验收阶段的竣工结算。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]