[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983781":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983781,714,2,"多选题","招标人可从()方面进行工程造价控制。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设置最高投标限价",true,{"key":16,"text":17,"correct":18},"B","变更中标合同价格",false,{"key":20,"text":21,"correct":18},"C","明确造价控制目标",{"key":23,"text":24,"correct":14},"D","编制合理的工程招标参考标底",{"key":26,"text":27,"correct":18},"E","设置严密、完善的合同条款","AD","招标人通常在工程造价控制目标的限额范围内，编制合理的工程招标参考标底或设置最高投标限价以控制工程的合同价格。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]