[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983780":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983780,714,2,"多选题","制订工程建设项目的进度计划时应考虑的可能影响工程实施进度的因素有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程实施条件",true,{"key":16,"text":17,"correct":14},"B","施工的资源投入",{"key":19,"text":20,"correct":14},"C","外部环境影响因素",{"key":22,"text":23,"correct":24},"D","投标人的财务状况",false,{"key":26,"text":27,"correct":14},"E","工程规模","ABCE","制订工程建设项目的进度计划时应考虑的可能影响工程实施进度的因素有：①工程实施条件；②工程规模；③工程施工工序；④施工作业面数量和工作面移交时间；⑤施工的资源投入；⑥外部环境影响因素。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]