[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983776":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983776,714,2,"多选题","下列有关勘察、设计和监理招标标段划分的说法正确的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","勘察项目一般不再划分标段",true,{"key":16,"text":17,"correct":14},"B","设计项目按照设计深度要求划分标段",{"key":19,"text":20,"correct":14},"C","监理招标项目的标段划分要结合施工标段的范围和特点",{"key":22,"text":23,"correct":24},"D","工程监理标段范围不能大于施工标段划分的范围",false,{"key":26,"text":27,"correct":14},"E","招标人不得通过细分标段、化整为零的方式规避招标","ABCE","D项，工程监理标段范围不能小于施工标段划分的范围，即不能出现一个施工标段由两个或两个以上监理单位同时监理的情况（特殊专业工程监理除外）；同时不同监理标段之间的工作范围要界定清晰、相互衔接，防止工作范围和责任交叉或空缺。项目发包人单位需要做好不同监理单位之间的协调管理。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]