[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983772":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983772,714,2,"多选题","关于施工承包方式，下列叙述正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","典型模式为“设计+施工”",false,{"key":16,"text":17,"correct":18},"B","建设周期一般较长，责任较难界定，设计与施工间的管理工作比较复杂",true,{"key":20,"text":21,"correct":18},"C","运用简单、成熟，对承发包双方要求不高",{"key":23,"text":24,"correct":14},"D","工程设计与施工责任及相应风险转移给一个总承包人",{"key":26,"text":27,"correct":14},"E","有利于工程设计与施工之间的衔接配合，可避免相互脱节而引起的差错、遗漏等","BC","A项，施工承包方式的典型模式表现为传统的“设计一施工”建设管理模式；D项，项目实施往往划分成一个或若干个单项、单位工程合同段承包，相应的工程责任和风险由一个或若干个承包人承担；E项属于设计一施工一体化承包方式的特点。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业实务","建筑工程",0]