[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},983761,714,1,"单选题","下列关于招标人自行招标的说法中，不符合《工程建设项目自行招标试行办法》规定的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标人应当具备编制招标文件和组织评标的能力",false,{"key":16,"text":17,"correct":14},"B","自行招标应当向有关行政监督部门备案",{"key":19,"text":20,"correct":14},"C","一次核准自行招标手续只适用于一个工程建设项目",{"key":22,"text":23,"correct":24},"D","招标人应当在发出中标通知书后的15日内向有关行政监督部门提交招标投标情况的书面报告",true,"D项，《工程建设项目自行招标试行办法》规定，依法必须招标的项目，招标人在确定中标人的15日内应该将项目招标投标情况书面报告提交招标投标有关行政监督部门。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]