[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983736":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},983736,714,1,"单选题","某机电产品国际招标项目，招标文件从3月1日开始发售，投标截止时间为3月21日，如果潜在投标人对招标文件有异议，最迟应当在()向招标人提出。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3月18日之前",false,{"key":16,"text":17,"correct":18},"B","3月11日之前",true,{"key":20,"text":21,"correct":14},"C","投标截止时间之前",{"key":23,"text":24,"correct":14},"D","评标结果公示期内","潜在投标人在阅读招标文件中产生疑问和异议的，可以按照招标文件规定的时间以书面提出澄清要求，招标人应当及时书面答复澄清。潜在投标人或其他利害人如果对招标文件的内容有异议，应当在投标截止时间10天前向招标人提出。本题中，如果潜在投标人对招标文件有异议，最迟应当在3月11日向招标人提出。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]