[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983735":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983735,714,1,"单选题","某国有企业采购生产工艺设备，因设备技术性能及要求难以描述，根据本项目特点，招标代理机构应当建议优先采取()方式。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","询价",false,{"key":16,"text":17,"correct":14},"B","竞争性谈判",{"key":19,"text":20,"correct":21},"C","两阶段招标",true,{"key":23,"text":24,"correct":14},"D","单一来源采购","因项目需求复杂或者首次采购，招标人无法准确拟定和提出项目范围、技术标准、报价规则或者商务条件，而自行编制招标文件，故需要采用两阶段招标。我国两阶段招标的规定比较适用需求技术和（或）商务条件比较复杂且招标人无法提出解决方案的项目，首先需要向潜在投标人征集解决方案并通过评审论证，优化合成统一的需求技术和（或）商务条件解决方案，既有利于第二阶段能够按统一口径公正比较、评价投标报价，也可以在第一阶段招标调研过程中通过招标投标双方交流调研，寻找优化合理的需求解决方案，避免双方在实质竞争的第二阶段或选择中标人后，为寻找合理和优化解决方案启动协商谈判程序，从而导致不公正定标和不正当交易。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]