[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983633":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},983633,714,1,"单选题","集中采购程序与分散采购程序的主要差别来源不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实质差别",true,{"key":16,"text":17,"correct":18},"B","集中归并",false,{"key":20,"text":21,"correct":18},"C","分批次重复采购",{"key":23,"text":24,"correct":18},"D","分主体实施合同","集中采购的程序与分散采购程序比较并无实质差别，主要差别都源于集中归并、分批次重复采购和分主体实施合同。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]