[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},983601,714,1,"单选题","下列关于采用综合评分法进行评标的表述中，错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","货物项目的价格分值与总分值的比重为10%～60%",true,{"key":16,"text":17,"correct":18},"B","采用综合评分法是在最大限度地满足招标文件实质性要求",false,{"key":20,"text":21,"correct":18},"C","执行统一价格标准的服务项目，其价格不列为评分因素",{"key":23,"text":24,"correct":18},"D","综合评分的主要因素是、价格、技术、财务状况、信誉、业绩、服务、对招标文件的响应程度，以及相应的比重或者权值等","A项，综合评分法货物项目的价格分值占总分值的比重（即权值）为30%～60%，服务项目的价格分值占总分值的比重（即权值）为10%～30%。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]