[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},983582,714,1,"单选题","世行、亚行贷款项目工程、货物和非咨询类服务招标的评标当中，价格评审的因素不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","付款时间",false,{"key":16,"text":17,"correct":18},"B","技术含量",true,{"key":20,"text":21,"correct":14},"C","运营成本",{"key":23,"text":24,"correct":14},"D","环境效益","世行、亚行贷款项目工程、货物和非咨询类服务招标的评标一般采用最低评标价法，不采用综合打分法。价格评审的因素包括：付款时间、交货期、运营成本、设备的效率和兼容性、零备件和服务的可获得性以及相关的培训、安全和环境效益。评审因素以货币化的形式体现。如果工期是关键因素，可以把提前完工给招标人带来的价值考虑进评标因素，但同时也要在合同条款中规定对未按期完工的承包商进行相应处罚。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]