[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983572":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},983572,714,1,"单选题","招标人应当自收到评标委员会提交的书面评标报告之日起()日内贷款方报送评标报告，取得其不反对意见。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","5",false,{"key":20,"text":21,"correct":18},"C","7",{"key":23,"text":24,"correct":18},"D","9","招标人应当自收到评标委员会提交的书面评标报告之日起3日内向贷款方报送评标报告，取得其不反对意见。贷款方对评标报告有反对意见的，招标人应当及时将贷款方的意见报相应的主管部门，并重新招标或者重新评标。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]