[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983564":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},983564,714,1,"单选题","项目单位应当在评审结束后()个工作日内将评审报告报财政部门审核。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","10",true,{"key":20,"text":21,"correct":14},"C","15",{"key":23,"text":24,"correct":14},"D","20","评审结束后，评审委员会应当撰写采购代理机构选聘评审报告。在评审报告上签名。项目单位应当在评审结束后10个工作日内将评审报告报财政部门审核。经财政部门审核同意后，项目单位应当发出中标通知书，同时将中标结果告知各未中标购代理机构。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]