[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983546":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983546,714,1,"单选题","依据《标准施工招标文件》（2007年版），下列合同文件中，在合同没有特别约定的前提下，合同文件的优先解释顺序排列正确的是()。①中标通知书；②投标函及投标函附录；③专用合同条款；④设计图纸；⑤合同协议书；⑥技术标准和要求；⑦已标价工程量清单；⑧通用合同条款。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","⑤①②③⑧⑥⑦④",false,{"key":16,"text":17,"correct":14},"B","⑤①③②⑦⑧⑥④",{"key":19,"text":20,"correct":21},"C","⑤①②③⑧⑥④⑦",true,{"key":23,"text":24,"correct":14},"D","⑤①②③⑧④⑥⑦","工程施工合同文件的组成部分主要包括：①合同协议书；②中标通知书；③投标函及投标函附录；④专用合同条款；⑤通用合同条款；⑥技术标准和要求；⑦设计图纸；⑧已标价工程量清单；⑨其他合同文件。上述合同文件应能互相补充和解释，如有不明确或不一致之处，以约定的优先次序为准。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]