[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983539,714,1,"单选题","机电产品国际招标项目采用综合评价法评标时，下列价格评分的规定符合要求的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","评标价最高的得5分，评标价最低的得50分，其余按插值法计算",false,{"key":16,"text":17,"correct":14},"B","价格得分=50-｜评标价-评标价均值｜\u002F评标价均值*100%*2",{"key":19,"text":20,"correct":21},"C","价格得分=最低评标\u002F评标价*50",true,{"key":23,"text":24,"correct":14},"D","评标价最低的得50分，按评标价名次排序，每递增一位减2分，直至20分止","应用综合评价法对机电产品国际招标项目进行评标时，价格打分可以采用公式计算或列表对比的方法，并应符合低价优先的原则，即评审后价格最低的应为最高分值，价格打分的最大可能分值和最小可能分值应当分别为价格满分和0分。价格得分=（最低评标价格\u002F评标价格）*价格分值权重*100。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]