[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983538":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983538,714,1,"单选题","采用综合评价法评标时，投标人的技术得分低于全体有效投标人的技术得分平均值()的，不得被确定为推荐中标人。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10%",false,{"key":16,"text":17,"correct":14},"B","20%",{"key":19,"text":20,"correct":21},"C","30%",true,{"key":23,"text":24,"correct":14},"D","40%","综合评价法明确规定投标人出现下列情形之一的，将不得被确定为推荐中标人：①投标人的评标价格超过全体有效投标人的评标价格平均值一定比例以上的；②投标人的技术得分低于全体有效投标人的技术得分平均值一定比例以上的。上述比例由招标文件具体规定，①项中所列的比例不得高于40%，②项中所列的比例不得高于30%。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]