[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983521":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},983521,714,1,"单选题","关于工程建设项目施工中标合同订立、履行过程中，对当事人的要求，下列说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标人应当自签订中标合同之日起15日内，向有关行政监管部门提交招标投标情况的书面报告",true,{"key":16,"text":17,"correct":18},"B","招标人不得在中标通知书中修改招标文件规定的开工时间",false,{"key":20,"text":21,"correct":18},"C","中标人确定前，招标人和投标人不能就投标价格等实质性内容进行谈判",{"key":23,"text":24,"correct":18},"D","中标合同备案后另行订立合同的，工程价款的结算应当以备案的合同为依据","A项，《招标投标法》第四十七条规定，依法必须进行招标的项目，招标人应当自确定中标人之日起15日内，向有关行政监督部门提交招标投标情况的书面报告。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]