[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983517":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},983517,714,1,"单选题","采用综合评分法评审的政府采购货物招标项目，中标候选人评审得分相同时，其排名应()顺序排列。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按照投标报价由低到高",true,{"key":16,"text":17,"correct":18},"B","按照技术指标优劣",false,{"key":20,"text":21,"correct":18},"C","由评标委员会综合考虑投标情况自定",{"key":23,"text":24,"correct":18},"D","按照投标报价得分由高到低","评审政府采购货物招标项目，采用综合评分法的，评审得分相同时，按投标报价由低到高顺序排列；得分且投标报价相同时，按技术指标优劣顺序排列；采用性价比法的，按商数得分由高到低顺序排列。得分相同的，按投标报价由低到高顺序排列。得分且投标报价相同的，按技术指标优劣顺序排列。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]