[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983476":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},983476,714,1,"单选题","关于投标文件的密封，下列说法中不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标人对投标文件修改的密封应按照招标文件的要求进行",false,{"key":16,"text":17,"correct":18},"B","投标文件的密封情况应在开标时由招标人代表或其监督人员负责检查",true,{"key":20,"text":21,"correct":14},"C","因密封不合格被招标人拒绝受理后，投标人仍可自行修补密封在投标截止时间前再次提交",{"key":23,"text":24,"correct":14},"D","招标文件根据需要增加的其他密封要求，投标人也必须遵守","B项，当投标人采用直接送达方式提交投标文件时，招标人应安排专人在招标文件指定地点接收投标文件（包括投标保证金），并详细记录投标文件送达人、送达时间、份数、包装密封、标识等查验情况。开标时，招标人依据招标文件规定的方式，组织投标人代表或招标人委托的公证人员对投标人自己和其他投标人的投标文件进行密封检查，其目的在于检查开标现场的投标文件密封状况是否与投标文件接收时的密封状况一致。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]