[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983463,714,1,"单选题","编制投标文件时，投标人应当对招标文件中提出的所有()作出响应。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","质量要求",false,{"key":16,"text":17,"correct":14},"B","投标报价",{"key":19,"text":20,"correct":21},"C","实质性要求和条件",true,{"key":23,"text":24,"correct":14},"D","服务技术指标","编制投标文件时，投标人应当对招标文件中提出的所有实质性要求和条件作出响应。实质性要求和条件是指招标文件中提出的投标资格、投标报价、施工工期（或货物供货期）、投标有效期、质量要求、技术标准和要求、服务技术指标、相关业绩等方面的要求。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]