[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983427":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983427,714,1,"单选题","关于投标文件的提交时间，下列说法正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投标文件必须在招标文件规定的投标开始前三天内送达",false,{"key":16,"text":17,"correct":14},"B","投标文件必须在招标文件规定的投标开始前一天内送达",{"key":19,"text":20,"correct":21},"C","投标文件必须在招标文件规定的投标截止时间之前送达",true,{"key":23,"text":24,"correct":14},"D","招标文件中没有对投标文件的提交时间做出具体规定","招标文件中通常会明确规定投标文件提交的时间，投标文件必须在招标文件规定的投标截止时间之前送达。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]