[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983404":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},983404,714,1,"单选题","在工程量清单的清单计价表格中，暂列金额属于()的内容。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施项目清单",false,{"key":16,"text":17,"correct":18},"B","其他项目清单",true,{"key":20,"text":21,"correct":14},"C","规费项目清单",{"key":23,"text":24,"correct":14},"D","税金项目清单","其他项目清单是指分部分项工程量清单、措施项目清单内容以外，因招标人的特殊要求而发生与拟建工程有关的其他费用项目和相应数量的清单。工程建设标准的高低、工程的复杂程度、工程的工期长短、工程的组成内容、发包人对工程管理要求等都直接影响其他项目清单的具体内容。其他项目清单包括：①暂列金额；②暂估价（包括材料暂估单价、工程设备暂估单价、专业工程暂估价）；③计日工；④总承包服务费等。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]