[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983403":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},983403,714,1,"单选题","对于复杂程度较高、风险较大的项目，不宜采用的合同类型为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总价合同",true,{"key":16,"text":17,"correct":18},"B","单价合同",false,{"key":20,"text":21,"correct":18},"C","可调单价合同",{"key":23,"text":24,"correct":18},"D","成本加酬金合同","如果项目的复杂程度较高，则意味着对承包人的技术水平要求较高，项目的风险较大。因此，承包人对合同的选择有较大的主动权，总价合同被选用的可能性较小。如果项目的复杂程度低，则发包人对合同类型的选择握有较大的主动权。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]