[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983392":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983392,714,1,"单选题","某依法必须招标的工程建设项目，计划开工日期十分紧迫，采用固定单价合同，其招标文件的桩基工程量清单数量为1000m 3 。招标人在投标截止前15d发出的招标文件澄清中修改了设计桩基直径，但没有修改桩基工程量清单数量。此时，投标人比较可行的做法是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按照修改后的桩基直径自行计算工程量清单数量并据此报价",false,{"key":16,"text":17,"correct":14},"B","按照原桩基工程量清单数量1000m 3 投标报价",{"key":19,"text":20,"correct":21},"C","向招标人提出异议，根据答复澄清，确定投标报价的工程数量",true,{"key":23,"text":24,"correct":14},"D","按照设计修改后的桩基直径计算投标报价的工程数量，并书面通知招标人","当投标人对招标文件有疑问时，可以要求招标人对招标文件予以澄清。招标人可以主动对已发出的招标文件进行必要的澄清和修改，对招标文件所作的澄清、修改构成招标文件的组成部分。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]