[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983381":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},983381,714,1,"单选题","BOT项目招标方案中，投标人的()条款如果涉及修改招标文件的核心内容，则一般会被招标人拒绝。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","融资方案",false,{"key":16,"text":17,"correct":18},"B","项目合同响应方案",true,{"key":20,"text":21,"correct":14},"C","移交方案",{"key":23,"text":24,"correct":14},"D","建设方案","BOT项目一般包括：①融资方案；②技术和管理方案，包括建设方案、运营维护方案和移交方案；③项目合同响应方案。其中，项目合同响应方案是指投标人对招标文件的项目合同中关于招标人与投标人双方权利、义务、责任安排条款的接受、补充、完善以及修改建议方案。投标人应对项目合同作出逐条响应，将建议修改的内容填入项目合同条款偏差表中。投标人的项目合同响应方案如果涉及修改核心或实质性条款，投标将被否决。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]