[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983366":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},983366,714,1,"单选题","在工程施工合同按照合同计价方式和风险分担情况划分的类型中，()计价方式一般适用于核定合同价格时，工程内容、范围、数量不清楚或难以界定的工程建设项目。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","固定总价合同",false,{"key":16,"text":17,"correct":14},"B","固定单价合同",{"key":19,"text":20,"correct":14},"C","可调价格合同",{"key":22,"text":23,"correct":24},"D","成本加酬金合同",true,"成本加酬金合同，指合同价格中工程成本按照实际发生额计算确定和支付，承包人的酬金可以按照合同双方约定额度或者比例的工程管理服务费和利润额计算确定，或按照工程成本、质量、进度的控制结果挂钩奖惩的浮动比例计算核定。这种合同计价方式一般适用于投标和核定合同价格时，工程内容、范围、数量不清楚或难以界定的工程建设项目。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]