[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983362":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983362,714,1,"单选题","()是为了解决现场发生的零星工作的计价而设立的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":14},"B","暂估价",{"key":19,"text":20,"correct":21},"C","计日工",true,{"key":23,"text":24,"correct":14},"D","分部分项工程费","计日工是承包人完成发包人提出的工程合同范围以外的零星项目或工作，按施工承包合同中规定的综合单价计价的一种方式。计日工是为了解决现场发生的零星工作的计价而设立的。计日工对完成零星工作所消耗的人工工时、材料数量、施工机械台班进行计量，并按照计日工表中填报的适用项目的单价进行计价支付。计日工适用的零星项目或工作一般是指合同规定之外的或因变更产生的、工程量清单中没有相应项目的额外工作，尤其是那些难以事先商定价格的额外工作。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]