[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983356":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},983356,714,1,"单选题","某生产企业拟采购一批工程车辆，为了充分体现绿色采购、低碳经济，以及政府对于车辆尾气排放和强制报废的要求，本次采购最适合的评标方法是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","全寿命周期成本计算法",true,{"key":16,"text":17,"correct":18},"B","栅栏评标法",false,{"key":20,"text":21,"correct":18},"C","性价比法",{"key":23,"text":24,"correct":18},"D","基于质量和成本的选择方法","全寿命周期成本计算法是将工程或货物的建设、采购、安装、运行、维修服务、更新改造，直至报废（废弃成本）的全寿命周期成本进行合并计算并折算为现值比较的评标方法。全寿命周期成本计算法可以全面反映一次采购的全寿命成本，采购的决策不仅仅考虑初始采购成本，还综合考虑项目的长期经济成本，使采购决策更加科学和客观。采用全寿命周期成本计算法仅考虑工程或货物的各项财务成本，而不考虑技术、品牌、人员、资质、业绩等因素。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]