[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983345":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},983345,714,1,"单选题","准备时间短，准备费用低的情况下，宜采用的合同类型为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总价合同",false,{"key":16,"text":17,"correct":14},"B","可调总价合同",{"key":19,"text":20,"correct":14},"C","单价合同",{"key":22,"text":23,"correct":24},"D","成本加酬金合同",true,"项目准备工作包括发包人的准备工作和承包人的准备工作。不同的合同类型需要的准备时间和准备费用不同。总价合同需要的准备时间和准备费用最高，成本加酬金合同需要的准备时间和准备费用最低。如抢险救灾等项目，给予发包人和承包人的准备时间都非常短，可以优先采用成本加酬金合同。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]