[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983329":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983329,714,1,"单选题","某依法必须招标的工程建设项目，在评标时发现投标人甲的安全生产许可证还有3天到期，对此，评标委员会比较客观和负责的做法是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","直接认定该投标文件为废标",false,{"key":16,"text":17,"correct":14},"B","认定该投标文件有效，继续对其评审",{"key":19,"text":20,"correct":21},"C","继续对该投标文件评审，并在评标过程中提示投标人",true,{"key":23,"text":24,"correct":14},"D","根据该投标人已完成项目的安全生产情况决定是否废标","《安全生产许可证条例》对建筑施工企业实行安全生产许可制度。企业未取得安全生产许可证的，不得从事生产活动。详细审查是审查委员会对通过初步审查的申请人的资格预审申请文件进行进一步审查。常见的详细审查因素和标准之一是：评标委员会应当审查安全生产许可范围是否与招标项目一致，执政期限是否有效，对安全生产许可证即将到期的应当在评标过程中提示投标人。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]